THERMAL INSULATION AND LAGGING HVAC
General Requirements
Thermal insulation shall be of approved material with thermal conductivity
not higher than 0.29 Btu/Hr/Ft2/F inch thickness measured at an average
temperature of 100 F. Thermal insulation shall be non-corrosive to the metal
water repellent, sustenance to vermin and easily cut and fitted to shape during application
The insulation should be resilient and retain its original shape
The insulation shall be provided with approved fire retardant vapour barrier
jacket to prevent the moisture penetration to the insulation
Vapour barrier shall also be applied to all joints and edges
The insulation shall be fixed on to the metal surface by means of an
approved adhesive compound that has no corrosive effect on the metal
and thoroughly applied to the metal surface and insulation
The insulation shall be carried out by skilled labourers and before thermal
insulation is applied, all metal surfaces shall be thoroughly cleaned and treated
with approved corrosion inhibitors
Piping Insulation
The insulation shall be secured to the piping by adequate number of
non-corrodable straps ¾” width at a center distance not more than one foot
The straps shall not in any case cut the insulation or the vapour seal
Wires shall not be acceptable
Insulation Material Thickness
Insulation material shall be Fiberglass 6 lb/Ft³ & shall have the following thickness
Pipe Size Up to 2” dia 2½” – 6” dia 8” dia & above
Chilled / Hot Water Pipes exposed to Sun 1” 2” 3”
Chilled/Hot Water Pipes in non-A/C areas 1” 1½” 2”
Chilled / Hot water pipes in A/C areas 3/8” 1” 1½”
Condenser Water (Cold) pipe from cooling tower to condenser exposed to sun 1”
Condensate drain pipe 3/8” 5/8”
All pipes running inside the A/C Plant room, A/H unit rooms and other
machinery rooms also inside the piping shaft or were they are exposed
to view shall be covered with heavy gauge “not less than 22” aluminium sheet
and in any case the designation and direction of fluid flow shall be suitable
marked on the surface at intervals. Weather and water proofing treatment to
be carried out prior to cladding
Duct Work Insulation
The thermal insulation used shall confirm to BS 5422: 1977 – BS 5422: 2009
The thermal insulation shall be made of fiberglass material with reinforced
aluminium foil external coating, factory applied with resin bonded internal
layer to give flat and resilient surface. The insulation of all duct works exposed
to outside and those in plant rooms shall be rigid slab type and for remaining
ducting flexible blanket type
Thermal conductivity shall not be more than 0.29 Btu/Hr. Sq. Ft. per inch thickness
measured at an average temperature at 100° F. The thermal insulation shall be non-corrosive
The insulation shall be provided with fiber retardant
vapour barrier jacket to prevent moisture and penetration
Vapour barrier shall also be applied to all joints and edges
The insulation shall be applied to metal surface by means of
approved non-corrosive adhesive compound.
The metal surface shall be treated with corrosion
inhibitors before the application of insulation
The density of insulation shall be minimum 1.5 lb./cu. ft. for flexible
blanket type and 3 lb./cu. ft. for rigid slab type and thickness
All duct works exposed outside and those in plant
room shall be insulated with 2” outside insulation
Duct works inside air-conditioned spaced shall be
insulated with one inch thick outside insulation
h. Insulation shall be secured to duct work with 2” x 2” G.I. sheet metal
strips of 22 gauge fixed to corners and tightened with wire 6” intervals
The strips may be suitably grooved to take the wire fasteners
In addition, all duct works exposed to outside be cladded with 24 gauge GI sheeting
and shall be treated for water proofing prior to cladding, i.e. wrap
the insulation with 0.5mm thick polyethylene sheet and secure the adhesive
All the duct works in plant room shall be finished with 8 Oz. Canvas
with 2 coats of fire retardant and water proof paint.
All external duct cladding shall be painted with one coat of primer suitable for
galvanized surface and two coats of final paint suitable for external application
Colour of paint should match the building and approved by the Engineer
Acoustic Duct Lining
Internal duct lining for acoustic insulation where applicable shall
not be less than 25 mm. thick fiberglass mat faced, flexible blanket
of fine fibers with securely bonded surface mat coated with black
neoprene or approved equal. Lining shall be applied with 100% coverage
of fire resistive approved adhesive compound and mechanical fastenings
according to the manufacturer’s instructions. Acoustic lining shall be
cleared 20 cm. on each side of the duct heater where applicable
Duct lining density shall be 24 kg/cubic meter