COOLING TOWERS Daily Routine work Operation and Maintenance

[​IMG]

[​IMG]

الحمد لله والصلاة والسلام على رسول الله وعلى آله وصحبه أجمعين

COOLING TOWERS Daily Routine work Operation and Maintenance

[​IMG]

A) Check and Record

1. Water level in the sump

2. Water meter reading

3. Fan motor voltage and ampere

4. Ambient temperatures. DB & WB

B) Check

1. Operation of the float valve

2. Over-flow

3. Blow down valve

4. Motor temperature by feeling with hand, if possible

C) Blow down to be carried out as recommended by Laboratory

D) Daily chemical dosage to be added / operation of chemical
treatment and bleeding units

E) Inspect for undue noise or vibration and any evidence of water leakage